0.6 100,000 60,000 0.4 100,000 40,000 EMV 60,000 - 40,000 20,000

EXAM ELABORATIONS Aug 29, 2025
Loading...

Loading document viewer...

Page 0 of 0

Document Text

50+ Examples of PMP Questions and Answers

  • A project has a 60% chance of a $100,000 profit and a 40 percent of a US

$100,000 loss. The Expected Monetary Value for the project is:

  • $100,000 profit
  • $60,000 loss
  • $ 20,000 profit
  • $40,000 loss
  • Expected Monitory Value (EMV) is computed by EMV = Probability × Impact.

Compute both positive and negative values and then add them:

0.6 × $100,000 = $60,000 0.4 × $100,000 = $40,000 EMV = $60,000 - $40,000 = $20,000

profit

  • Assuming that the ends of a range of estimates are +/- 3 sigma from the
  • mean, which of the following range estimates involves the LEAST risk?

  • 30 days, plus or minus 5 days
  • 22 – 30 days
  • Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days
  • Mean of 28 days
  • The estimate with the smallest range is less risky. 1 / 3

  • If a risk has a 20 percent chance of happening in a given month, and the
  • project is expected to last five months, what is the probability that the risk event will occur during the fourth month of the project?

  • Less than 1 percent
  • 20 percent
  • 60 percent
  • 80 percent
  • An accepted deadline for project approaches. However, the project
  • manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

  • Additional resources using the contingency fund
  • Escalation approval to use contingency funding
  • Team overtime to meet the schedule
  • Corrective action based on causes
  • The risk will be identified during which risk management process(es)?
  • Perform Quantitative Risk Analysis and Identify Risks
  • Identify Risks and Monitor and Control Risks
  • Perform Qualitative Risk Analysis and Monitor and Control Risks
  • Identify Risks
  • What is meant by RACI? 2 / 3
  • Responsible, Accountable, Confirm, Inform
  • Recommended, Accountable, Consulted, Inform
  • Responsible, Accountant, Consulted, Inform
  • Responsible, Accountable, Consulted, Inform
  • The RACI chart is an example of the Responsibility Assignment Matrix (RAM), which shows the relationship between activities and the team members.

  • Which of the following statement is true about a Program?
  • A Program is a group of related projects
  • A Program is a group of unrelated projects
  • A Program is a part of a big project
  • None of the above

Reference: The PMBOK® Guide, 5th Edition, Page 9

  • The project manager meets with the project team to review lessons learned
  • from previous projects. In what activity is the team involved?

  • Performance management
  • Scope identification
  • Risk identification
  • Project team status meeting
  • During a bidder conference, you see that one bidder is your close friend.
  • What should your next step be?

  • / 3

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: EXAM ELABORATIONS
Added: Aug 29, 2025
Description:

50+ Examples of PMP Questions and Answers 1. A project has a 60% chance of a $100,000 profit and a 40 percent of a US $100,000 loss. The Expected Monetary Value for the project is: 1. $100,000 prof...

Get this document $30.00