50+ Examples of PMP Questions and Answers
- A project has a 60% chance of a $100,000 profit and a 40 percent of a US
$100,000 loss. The Expected Monetary Value for the project is:
- $100,000 profit
- $60,000 loss
- $ 20,000 profit
- $40,000 loss
Expected Monitory Value (EMV) is computed by EMV = Probability × Impact.
Compute both positive and negative values and then add them:
0.6 × $100,000 = $60,000 0.4 × $100,000 = $40,000 EMV = $60,000 - $40,000 = $20,000
profit
- Assuming that the ends of a range of estimates are +/- 3 sigma from the
- 30 days, plus or minus 5 days
- 22 – 30 days
- Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days
- Mean of 28 days
mean, which of the following range estimates involves the LEAST risk?
The estimate with the smallest range is less risky. 1 / 3
- If a risk has a 20 percent chance of happening in a given month, and the
- Less than 1 percent
- 20 percent
- 60 percent
- 80 percent
- An accepted deadline for project approaches. However, the project
- Additional resources using the contingency fund
- Escalation approval to use contingency funding
- Team overtime to meet the schedule
- Corrective action based on causes
- The risk will be identified during which risk management process(es)?
- Perform Quantitative Risk Analysis and Identify Risks
- Identify Risks and Monitor and Control Risks
- Perform Qualitative Risk Analysis and Monitor and Control Risks
- Identify Risks
- What is meant by RACI? 2 / 3
project is expected to last five months, what is the probability that the risk event will occur during the fourth month of the project?
manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?
- Responsible, Accountable, Confirm, Inform
- Recommended, Accountable, Consulted, Inform
- Responsible, Accountant, Consulted, Inform
- Responsible, Accountable, Consulted, Inform
- Which of the following statement is true about a Program?
- A Program is a group of related projects
- A Program is a group of unrelated projects
- A Program is a part of a big project
- None of the above
The RACI chart is an example of the Responsibility Assignment Matrix (RAM), which shows the relationship between activities and the team members.
Reference: The PMBOK® Guide, 5th Edition, Page 9
- The project manager meets with the project team to review lessons learned
- Performance management
- Scope identification
- Risk identification
- Project team status meeting
- During a bidder conference, you see that one bidder is your close friend.
- / 3
from previous projects. In what activity is the team involved?
What should your next step be?