3M 303 - Work Center Supervisor Exam
What does CSMP stand for - ANSWER-Current ship's maintenance project
How are JSN's assigned - ANSWER-Automatically by the OMMS system
Who iz the ship's 3M Manager - ANSWER-Executive officer
If an MRC states it will take 0.3 man hours to accomplish, how long will it take - ANSWER-18 minutes
What is the only section of an MRC that a Work Center Supervisor can authorize changesow often - ANSWER-Tools, parts, materials, and test equipment
How is the start IEM annotated on the Cycle PMS Schedule? - ANSWER-It is not
How is the start of IEM annotated on the Quarterly PMS Schedule - ANSWER-Virticle red line
What is SKED used for - ANSWER-Used to automate the PMS scheduling process
Who is responsible for installing a "FR" - ANSWER-The work center supervisor
What color are classified MRCs - ANSWER-Pink
What color iss used tk schedule Lay Up and Start Up maintenance - ANSWER-Green
How often is the weekly schedule updated - ANSWER-Daily
How often is the Quarterly schedule updated - ANSWER-Weekly
Who must initial lineouts on MIPs - ANSWER-Ddepartment head
How long can a SFWL (MCAP) remain open until it has to be deferred - ANSWER-30 days
How is underway time annotated on the quarterly board - ANSWER-The scheduled underway dates are shded in at the top of the board
How many quarters are listed on the Cycle schedule - ANSWER-24 quarters