3M WORK CENTER SUPERVISOR
Which of the following are not provided under the 3-M PMS program ? - ANSWER- Management of technical publications stored within the work center
Which of the following is a responsibility of the Department Head? - ANSWER-Authorize in writing any equipment placed in Inactive Equipment Maintenance status
When tagging out a piece of equipment that could jeopardize safety of personnel or endanger equipment , system or components , which type of tag would you use ? - ANSWER-Danger Tag
What documentation must be verified , prior to conducting maintenance on a piece of equipment using portable power tools ? - ANSWER-A current safety inspection from the electrical tool issue room
A category B (Technical FBR) is used for what purpose ? - ANSWER-Used to report technical discrepancies inhibiting PMS performance.
What is the primary source data for maintenance scheduling software ? - ANSWER- NAVY PMS CD/DVDs
For metered events , how often must meter be updated in SKED? - ANSWER-Weekly or when required
How many sections/parts make up a ragout binder ? - ANSWER-6
What does PPE stand for ? - ANSWER-Personal protective equipment
This control document is used for administering labels ( OOC and CAL ) . It provides sequential listing of all OOC and CAL instruments? - ANSWER-Instrument Log
If there is no IEM maintenance provided , the activity will request assistance from what specific entity in obtaining direction ? - ANSWER-Type commander (TYCOM)
What instruction dictates the requirement for hazmat container labeling ? - ANSWER- OPNAVINST 5100.19 (series)
What is the three segment code used for cataloging MRCs? - ANSWER-SYSCOM MRC control number
- / 2
What is the purpose of a maintenance requirement card ? - ANSWER-Provide detailed procedures for performing maintenance requirements
Which of the following are NOT identification markers on shipboard HAZMAT containers ? - ANSWER-SYSCOM Control Number
What reference is designed to provide the user with a ready reference for all aspects concerning the 3-M program? - ANSWER-NAVSEAINST 4790.8C
What is purpose of the current ships maintenance project (CSMP) ? - ANSWER- Provides shipboard maintenance managers with a consolidated listing of deferred maintenance to identify the material condition of the ship
Who is responsible for ensuring that personnel assigned to their respective areas understand and comply with the Tag Out Users manual. - ANSWER-Department Head
Who can complete weekly close out of maintenance in the absence of the DIVO? -
ANSWER-LCPO
Who serve as the overall 3-M program technical expert and advisor ? - ANSWER-3MC
What does APL stand for ? - ANSWER-Allowance parts list
What day must all maintenance be closed out for the week? - ANSWER-First workday of the week
What is a 7 character alphanumeric code which is assigned to each MRC? - ANSWER- SYSCOM MRC Control Number
Which of the following is NOT listed on the list of Effective Pages? - ANSWER- Situational requirement report
What documentation supersedes all planned or preventive maintenance systems or programs ? - ANSWER-PMS
Who is responsible for reviewing PMS assignments , perform quality maintenance IAW procedural documentation ? - ANSWER-Maintenance Person
When the maintenance person does not fully understand , or identifies incorrect information on an MRC, who does the MP notify ? - ANSWER-WCS
Who documents maintenance accomplished by outside activity ? - ANSWER-SMMO
What does IMA stand for ? - ANSWER-Intermediate maintenance activity
- / 2