ACI CONCRETE FIELD TESTING
CERTIFICATION GRADE I EXAM NEWEST 2025
ACTUAL EXAM COMPLETE 100 QUESTIONS
AND CORRECT DETAILED ANSWERS
(VERIFIED ANSWERS) |ALREADY GRADED A+
---
- For concrete with aggregates less than 3 inches, the
thermometer must remain in the fresh concrete sample a minimum of 5 minutes or until the temperature reading stabilizes. (T/F)
ANSWER: F (2 minutes but not more than 5)
- The temperature measuring device must be accurate to within
0.1°. (T/F)
ANSWER: F (1°F or 0.5°C)
- The temperature measuring device shall have a capacity of
measuring temperature of freshly mixed concrete throughout a
range of ___ to ___ F:
ANSWER: 30° to 120°F
- | P a g e
- A composite sample is not needed if only the temperature test
is being run. (T/F)
ANSWER: T
- The temperature of fresh concrete in a placement must be
measured by inserting a thermometer into the top six inches of concrete. (T/F)
ANSWER: F (Does not specify aggregate size; ASTM C1064
requires a minimum of 3 in. submersion)
- ASTM C1064 states the container used to measure the
- inches of concrete. (T/F)
temperature of concrete must be large enough to provide at least
ANSWER: F (3 inches or must be 3x the nominal max size)
- The temperature of the concrete is recorded to the nearest ___
°F:
ANSWER: 1°F
- | P a g e
- Calibrate the temperature measuring device at least ___, or
whenever there is a question of accuracy:
ANSWER: Annually
- After the thermometer is placed in the concrete, what should
be done?
ANSWER: Gently press concrete around the thermometer
- According to ASTM C1064, what is one reason to take the
temperature of concrete?
ANSWER: Verify conformance
- It is allowable to remove the temperature measuring devices
from the freshly mixed concrete to read the temperature if you cannot see the reading. (T/F)
ANSWER: F
- | P a g e
- The maximum allowable time between obtaining the first
and last portions of the composite sample may not exceed 5 minutes. (T/F)
ANSWER: F (15 minutes)
- Start molding specimens for strength tests within 30 minutes
after fabricating the composite sample. (T/F)
ANSWER: F (15 minutes)
- The composite concrete sample must be protected from the
sun, wind, contamination, and rapid evaporation. (T/F)
ANSWER: T
- If the concrete contains aggregate larger than those that are
appropriate for the size of mold or equipment used, the sample should be wet sieved before making the test. (T/F)