The sensor of the temperature measuring device shall be submerged a minimum of _____ in. [_____mm] into the freshly mixed concrete. - Answer-3 in. [75 mm]
The temperature measuring device shall have a capacity of measuring temperature of freshly mixed concrete to +- _____ degrees F [+- _____ C] throughout a range of _____. - Answer-1 degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]
The temperature measuring device shall be calibrated _____, or whenever there is a question of _____. - Answer-Annually, accuracy
The temperature of concrete may be measured in a wheelbarrow. True or False? - Answer-True
- / 3
- | P a g e
The temperature of concrete may be measured in a wall form. True of False - Answer-True
A composite sample of concrete is required even if the only purpose for obtaining the sample is to determine temperature. True of False? - Answer-False
What must be done to the sample container prior to sampling the concrete? - Answer-Dampen (with water)
What must be done to the concrete surrounding the temperature measuring device after the device is submerged in the fresh concrete. - Answer-Gently press the concrete around the temperature measuring device at the surface of the concrete
How long must the temperature measuring device remain in the freshly mixed concrete? - Answer-At least 2 minutes but not more than 5 minutes
After the temperature of the concrete is read, what is required? - Answer-Reporting of temperature
- / 3
- | P a g e
The temperature of concrete is reported to the nearest _____ degrees F [_____ C] - Answer-1 degree F [0.5 C]
According to ASTM C1064, what is one reason to take the temperature of concrete? - Answer-Verify conformance to a specified requirement for temperature of concrete
A maximum temperature of freshly mixed concrete is specified in ASTM C1064. True of False? - Answer-False
The sample of concrete used for temperature determination must be rodded 25 times. True or False? - Answer-False
Sampling by this method is required when tests are to be made to determine _____ with specification requirements.
- Answer-Compliance
This method covers sampling from four types of mixtures which are _____, _____, _____, and _____. - Answer- Stationary mixers, paving mixers, revolving drum mixers, and open top mixers
- / 3