ACI CONCRETE FIELD TESTING TECHNICIAN-

GRADE I 2024 LATEST WITH QUESTIONS &

CORRECT ANSWERS GRADED A+

The sensor of the temperature measuring device shall be submerged a minimum of _____ in. [_____mm] into the freshly mixed concrete. - ANSWER-3 in. [75 mm]

The temperature measuring device shall have a capacity of measuring temperature of freshly mixed concrete to +- _____ degrees F [+- _____ C] throughout a range of _____. - ANSWER-1 degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]

The temperature measuring device shall be calibrated _____, or whenever there is a question of _____. - ANSWER-Annually, accuracy

The temperature of concrete may be measured in a wheelbarrow. True or False? - ANSWER-True

The temperature of concrete may be measured in a wall form. True of False - ANSWER-True

A composite sample of concrete is required even if the only purpose for obtaining the sample is to determine temperature. True of False? - ANSWER-False

What must be done to the sample container prior to sampling the concrete? - ANSWER-Dampen (with water)

  • / 3

What must be done to the concrete surrounding the temperature measuring device after the device is submerged in the fresh concrete. - ANSWER-Gently press the concrete around the temperature measuring device at the surface of the concrete

How long must the temperature measuring device remain in the freshly mixed concrete? - ANSWER-At least 2 minutes but not more than 5 minutes

After the temperature of the concrete is read, what is required? - ANSWER- Reporting of temperature

The temperature of concrete is reported to the nearest _____ degrees F [_____ C] - ANSWER-1 degree F [0.5 C]

According to ASTM C1064, what is one reason to take the temperature of concrete? - ANSWER-Verify conformance to a specified requirement for temperature of concrete

A maximum temperature of freshly mixed concrete is specified in ASTM C1064.True of False? - ANSWER-False

The sample of concrete used for temperature determination must be rodded 25 times. True or False? - ANSWER-False

Sampling by this method is required when tests are to be made to determine _____ with specification requirements. - ANSWER-Compliance

This method covers sampling from four types of mixtures which are _____, _____, _____, and _____. - ANSWER-Stationary mixers, paving mixers, revolving drum mixers, and open top mixers 2 / 3

The maximum allowable time between obtaining the first and final portions of a composite sample is _____ minutes. - ANSWER-15

Portions of a composite sample shall be thoroughly remixed bfore beginning tests on the sample. True of False? - ANSWER-True

The maximum elapsed time allowed between obtaining the final portion of the composite sample and beginning the tests for slump, temperature, and air content is _____ minutes. - ANSWER-5

The molding of strength test specimens shall begin within _____ minutes after fabricating the composite sample. - ANSWER-15

The concrete sample must be protected from contamination and _____. - ANSWER-Rapid evaporation

The minimum size sample for making strength test specimens is _____. - ANSWER-28 L (1ft^3)

When sampling from a stationary mixer, the batch must be sampled at _____ or more regularly spaced intervals during discharge of the middle portion of the batch

- ANSWER-2

The composite sample for a paving mixer must represent a minimum of _____ different portions of the batch of concrete taken from the pile after discharge. -

ANSWER-5

  • / 3

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Questions & answers
Added: Sep 7, 2025
Description:

ACI CONCRETE FIELD TESTING TECHNICIAN- GRADE I 2024 LATEST WITH QUESTIONS & CORRECT ANSWERS GRADED A+ The sensor of the temperature measuring device shall be submerged a minimum of _____ in. [_____...