The sensor of the temperature measuring device shall be submerged a minimum of _____ in. [_____mm] into the freshly mixed concrete. - ANSWER- 3 in. [75 mm]

The temperature measuring device shall have a capacity of measuring temperature of freshly mixed concrete to +- _____ degrees F [+- _____ C] throughout a range of _____. - ANSWER- 1 degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]

The temperature measuring device shall be calibrated _____, or whenever there is a question of _____. - ANSWER- Annually, accuracy

The maximum allowable time between obtaining a composite sample's first and final portions is _____ minutes. - ANSWER- 15

Portions of a composite sample shall be thoroughly remixed before beginning tests on the sample. True or False? - ANSWER- True

  • / 4

The maximum elapsed time allowed between obtaining the final portion of the composite sample and beginning the tests for slump, temperature, and air content is _____ minutes. - ANSWER- 5

The molding of strength test specimens shall begin within _____ minutes after fabricating the composite sample. - ANSWER- 15

The concrete sample must be protected from contamination and _____. - ANSWER- Rapid evaporation

The minimum size sample for making strength test specimens is _____. - ANSWER- 28 L (1ft^3)

When sampling from a stationary mixer, the batch must be sampled at _____ or more regularly spaced intervals during discharge of the middle portion of the batch

- ANSWER- 2

The composite sample for a paving mixer must represent a minimum of _____ different portions of the batch of concrete taken from the pile after discharge. -

ANSWER- 5

When sampling from a revolving drum truck mixer, concrete must be sampled at a minimum of _____ regularly spaced intervals during discharge of the middle portion of this batch. - ANSWER- 2

Concrete samples from a truck mixer must be obtained before any water or admixtures are added to the mixer at the job site. True or False? - ANSWER- False

The composite samples from a truck mixer must be obtained from the _____ portion of the batch. - ANSWER- Middle 2 / 4

When the concrete contains aggregate larger than that permitted for a particular test method, the sample of concrete must be _____ _____ before making the test. - ANSWER- Wet sieved

The temperature of concrete may be measured in a wheelbarrow. True or False? - ANSWER- True

The temperature of concrete may be measured in a wall form. True or False - ANSWER- True

A composite sample of concrete is required even if the only purpose for obtaining the sample is to determine temperature. True or False? - ANSWER- False

What must be done to the sample container before sampling the concrete? - ANSWER- Dampen (with water)

What must be done to the concrete surrounding the temperature measuring device after the device is submerged in the fresh concrete. - ANSWER- Gently press the concrete around the temperature measuring device at the surface of the concrete

How long must the temperature measuring device remain in the freshly mixed concrete? - ANSWER- At least 2 minutes but not more than 5 minutes

After the temperature of the concrete is read, what is required? - ANSWER- Reporting of temperature

The temperature of concrete is reported to the nearest _____ degrees F [_____ C] - ANSWER- 1 degree F [0.5 C] 3 / 4

According to ASTM C1064, what is one reason to take the temperature of concrete? - ANSWER- Verify conformance to a specified requirement for temperature of concrete

A maximum temperature of freshly mixed concrete is specified in ASTM C1064.True or False? - ANSWER- False

The sample of concrete used for temperature determination must be rodded 25 times. True or False? - ANSWER- False If, after consolidation of the final layer, the concrete level is 1/2 in. (13 mm) above the top of the measure, what should be done? - ANSWER- Remove a representative portion of the excess concrete with a trowel or scoop

After consolidation of the final layer, an excess of concrete ____ above the top of the measure is considered optimum. - ANSWER- 1/8 in. [3 mm]

After completing the strike-off procedure, what must be done before weighing the measure and sample? - ANSWER- Clean off any excess concrete

The pressure method of determining air content can be used on concrete containing _____ _____ aggregate. - ANSWER- Relatively Dense

The pressure method of determining air content cannot be used on concrete containing the following types of aggregates, _____, _____, _____. - ANSWER- Lightweight, air-cooled blast furnace slag, or aggregates of high porosity

What is the minimum allowable capacity of the measuring bowl used in this test method? - ANSWER- 6 L (0.20 ft^3)

  • / 4

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Questions & answers
Added: Sep 7, 2025
Description:

ACI CONCRETE FIELD TESTING TECHNICIAN GRADE 1 ACTUAL EXAM WITH QUESTIONS AND WELL-VERIFIED CORRECT ANSWERS | ALREADY GRADED A+ | ACI CONCRETE FIELD TESTING TECHNICIAN LATEST VERSION 2025 |BRAND NEW...

Get this document $30.00