ACI Field Grade One 83 Questions with Correct Answers 100% Verified

Sampling:

The maximum allowable time between obtaining the first and final portions of a composite sample

is: - Correct Answers 15 minutes

Sampling:

T/F: Concrete samples must be obtained before any water or admixtures are added to the mixture at the job site - Correct Answers False

Sampling:

When sampling from a paving mixer, obtain samples from at least ___ different portions of the pile and combine them into one composite sample for test purposes - Correct Answers 5

Sampling:

When sampling from a revolving dump truck, how many portions should be collected? - Correct Answers 2 or more

Sampling:

T/F: Samples for strength should be taken before 10% or after 90% of the batch has been discharged

  • Correct Answers False

Sampling:

The concrete sample must be protected from ____and ____ - Correct Answers sun and wind

Sampling:

Portions for a composite sample shall be combined and thoroughly remixed before beginning tests - Correct Answers True

Sampling:

What is the minimum sample size? - Correct Answers 1 ft^3

Sampling: 1 / 2

T/F: samples smaller than 1 ft^3 are allowed on routine air content, temp, and slump tests - Correct Answers False

Sampling:

after obtaining the final portion of the composite sample, the maximum allowable time before beginning tests for slump, temp, and air cont is ____ - Correct Answers 5 minutes

Sampling:

Start molding strength samples within ___ mins after fabricating the composite sample - Correct Answers 15 mins

Sampling:

When the concrete contains aggregate larger than permitted for a particular test method, the sample of concrete can be _____ before testing - Correct Answers wet

Sampling:

Can a 2" coarse aggregate concrete sample for unit testing be wet sieved? - Correct Answers No

Sampling:

What are 5 types of equipment this standard covers for sampling? - Correct Answers Non-agitating equipment Agitating equipment stationary equipment truck mixtures paving equipment continuous mixers

Temperature:

T/F: A composite sample is not required for measuring the temperature of fresh concrete - Correct Answers True

Temperature:

Can temp be measured in the formwork? - Correct Answers yes

  • / 2

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: EXAM ELABORATIONS
Added: Sep 5, 2025
Description:

ACI Field Grade One 83 Questions with Correct Answers 100% Verified Sampling: The maximum allowable time between obtaining the first and final portions of a composite sample is: - Correct Answers 1...

Get this document $30.00