APM PMQ Exam revision Bok7 2025 Revised

Study Guides Aug 26, 2025
Loading...

Loading document viewer...

Page 0 of 0

Document Text

APM PMQ Exam revision Bok7 2025 Revised Latest Update 2025-2026 270 Questions and 100% Verified Correct Answers Guaranteed A+

  • types of project cost: - CORRECT ANSWER: • Direct
  • • Indirect • Fixed • Variable

A project risk is defined as.... - CORRECT ANSWER: The exposure of stakeholders to the consequences of variations in outcome. It is the overall risk affecting the whole project, defined by components associated with risk events, other sources of uncertainty and associated dependencies , to be managed at a strategic level.

A risk event is defined as.... - CORRECT ANSWER: An uncertain event or set of

circumstances that should it occur will have an effect on the achievement of one or more project objectives.

Advantages of project management software - CORRECT ANSWER: Excellent

reporting tool What-if analysis Progress tracking Quick calculations

Are all project management processes linear? e.g. completed once and not repeated? -

CORRECT ANSWER: No some may be constantly repeated throughout the project e.g.

estimation of project budget, or updating of business case, re-baselining of requirements, ongoing risk management.

  • / 4

Areas of law to consider - CORRECT ANSWER: Health and Safety

Employment Contract Data protection Freedom of information

Arguments against the use of EVM - CORRECT ANSWER: Requires frequent

information on costs Forecasts are based on no corrective action Can lead to a lack of focus on quality Oversimplified Doesn't work for some project methods (agile)

Barriers affecting communication - CORRECT ANSWER: Clarity of ideas

Purpose Environment Background Delivery Body Language

Baseline budget - CORRECT ANSWER: • Everything is reported and measured against the baseline • Allows expectation of project spending

Baseline project budget structure - CORRECT ANSWER: • Project budget

• 2 X Reserves • Cost Baseline • Control Accounts 2 / 4

• Work Package estimates • Activity estimates

Benefits Management - CORRECT ANSWER: The identification, definition, planning,

tracking and realisation of business benefits

Benefits of a formal communications plan - CORRECT ANSWER: Understanding of

roles and responsibilities Reduced potential for conflict due to misunderstanding Enhanced confidence within project team and stakeholders Consistent transfer of project information Higher sense of ownership and commitment within the team

Benefits of a project lifecycle - CORRECT ANSWER: Consistency

High Level Planning.More effective planning Go/no go decisions.Improved decision-making Phase end reviews.Improved governance Manage funding Lesson Learned. Improved communication

Management focus on the early phases

Benefits of a project review - CORRECT ANSWER: • Allow for more informed decision- making • Increases stakeholder confidence • Allow for timely implementation of corrective action • Allows for an objective review of the project health • Sharing of lessons learned 3 / 4

• Increased chance of project success • Rigorous governance

Benefits of EVM - CORRECT ANSWER: Useful for monitoring, tracking and

reforecasting cost and schedule, and for paying suppliers on the basis of work done.

Simpler project reporting (KPIs) Highlight estimating errors Facilitate forecasting of cost and time Facilitates tighter controls of direct costs Help justify corrective action Identifies where early termination of project is required

Benefits of governance - CORRECT ANSWER: Clear reporting and escalation criteria Independent audits and reviews Empowerment to make appropiate decisions Culture of improvement and disclosure Engaged and more trusting stakeholders Assures stakeholders Achieve return on investment. Optimisation of investment.Resource usage justified.No unacceptable risks.Avoidance of common failures Better communication Delivery credibility Minimising risk Regulatory compliance

  • / 4

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Study Guides
Added: Aug 26, 2025
Description:

APM PMQ Exam revision Bok7 2025 Revised Latest Update 2025-2026 270 Questions and 100% Verified Correct Answers Guaranteed A+ 4 types of project cost: - CORRECT ANSWER: • Direct • Indirect • ...

Get this document $30.00