Question 1: Telecommunications Project Management
CORRECT ANSWER: Typically two distinct processes: Design and implementation/installation
Question 2: Design PM Responsibilities
CORRECT ANSWER: -Review expression of interest
from client -Perform a user needs analysis -Perform site surveys and meet with client -Generate preliminary design submittals -Respond to/incorporate client comments -Prepare final bid documents/RFP and engineer's cost estimate -Issue final RFP package to client -Client makes RFP available to potential bidders
Question 3: Implementation of TPM
CORRECT ANSWER: -Review client RFP and
associated documents -Perform site surveys -Organize and submit bidder's questions to client -Organize and
- | Page
submit final proposal/bid documents to client -Client awards contract gives contractor notice to proceed - Contractor mobilizes -Project implementation begins
Question 4: Project
CORRECT ANSWER: Is a temporary endeavor that has
a definite beginning and end whose end result is the delivery of a product or service
Question 5: Projects are governed by what: CORRECT ANSWER: Constraints: -Cost -Time - Money -Quality -Risk -Tech -Safety -Etc.
Question 6: ICT professionals are responsible for
knowing:
CORRECT ANSWER: -Background of the project and
project relationships -Project milestones -Specific roles within the project -Specific tasks expected to be performed -Challenges and issues unique to the project - Methods and techniques planned to be used -Applicable standards -Security requirements -Safety requirements -
- | Page
Evaluation of of work process -Recordkeeping process and requirements -Status and monitoring process of both the company and customer -Required meetings
Question 7: Project stakeholder
CORRECT ANSWER: A person who can positively or
negatively affect or be affected by the project
Question 8: Stakeholder analysis must be done for:
CORRECT ANSWER: Individual projects
Question 9: Sponsor
CORRECT ANSWER: Person or group that provides
financial support for the project
Question 10: Portfolio Managers/Portfolio Review Board
CORRECT ANSWER: Persons responsible for strategic
planning of projects and programs for an organization.Ensure the projects and programs meet the long term objectives of the organization
- | Page
Question 11: Clients/Users
CORRECT ANSWER: Persons or organizations that
will be the primary beneficiaries of the completed project
Question 12: Sellers
CORRECT ANSWER: Typically vendors, suppliers, or
contractors and are external organizations that enter into contract to provide components or services
Question 13: Business Partners
CORRECT ANSWER: External companies but have a
relationship with the enterprise. Provide specialized expertise or fill a specified role such as installation, customization, training or support
Question 14: Operations Managers
CORRECT ANSWER: Individuals who have a
management role in a core business. Incorporates