Bicsi Technician Exam Questions And Answers With Verified Solutions 100% Correct!!!L Rating - ANSWER✔✔A firestops ability to provide a smoke stop. (air leakage rate)
To avoid damaging cable jacket, how often must you securely fasten electrical nonmetallic tubing (ENT) - ANSWER✔✔3 Feet so it does not damage the cable
What is the minimum dedicated power requirement of a telecommunications enclosure - ANSWER✔✔120 V ac/20
The clearance behind the PBB when mounted, should be no less than- - ANSWER✔✔2inch clearance behind the PBB when mounted
When installing a plywood backboard, you should use galvanized screws that are a minimum of ______ longer than the depth of the wall covering, including the plywood - ANSWER✔✔0.5in
The use of under carpet telecommunications cable should be limited to: -
ANSWER✔✔The interconnection point between horizontal cabling and UTC is a transition point (TP)
Two 90-degree bends are allowed in any one conduit segment. A third bend may be acceptable under certain situations - ANSWER✔✔Runs under 33 feet
- / 2
When installing racks and cabinets on an access floor, what should they be secured to? - ANSWER✔✔The frame
When placing cabinets on an access floor, how should the cabinets be aligned? - ANSWER✔✔One edge flush with the floor tile cut line
What is a telecommunications enclosure TE used for? - ANSWER✔✔May be used to provide a suitable option for moves, adds, and changes without compromising infection control measures and other restrictions
What size threaded rod would you typically use in a heavy duty ladder rack installation? - ANSWER✔✔5/8in
A supplemental bonding network within an ER or data center consisting of a set of conductors formed into a grid is often associated with what? - ANSWER✔✔Access flooring
Which type of anchor requires a hole to be drilled into the floor where the attachment is to be made? - ANSWER✔✔Expansion anchors
Min seperation from electric motors and transformers? - ANSWER✔✔48"
During which phase of the project would you determine cable labeling requirements? - ANSWER✔✔Pre-construction Phase
What type of documentation uses the original floor plans and reflects the actual installed outlet locations, cables, length, and firestopping materials? - ANSWER✔✔Record drawings