Question 1: July 1 2005, service techs shall possess or work

under someone who has a current certification indicating he or she has passed the ?

CORRECT ANSWER : California UST service technician exam

Question 2: ICC cert must be renewed every?

CORRECT ANSWER : 24 months

Question 3: Service techs must posses or be employed by a

person who has the appropriate contractors license unless?

CORRECT ANSWER : The individual has a Tank testing licens

Question 4: Service tech is defined by any individual who?

CORRECT ANSWER : Test UST monitoring equipment

Trouble shoots UST systems Installs UST monitoring equipment

Question 5: If the manufacturer training no longer exist , the

local angency may?

  • | Page

CORRECT ANSWER : Approve comparable alternat training .

Question 6: UST includes?

CORRECT ANSWER : Tank and connected piping

Question 7: What is considered and UST

CORRECT ANSWER : petroleum storage tank

Question 8: What UST system meets the requirements for

secondary containment?

CORRECT ANSWER : Doubled wall tanks

Question 9: According to title 23; the following piping

components if installed after July 1 1987 must have secondary containment

CORRECT ANSWER: Pressured product piping

Question 10: Considered "pipe" on tanks installed after July 1

2003

CORRECT ANSWER : Pressured product piping and below

ground vapor recovery

  • | Page

Question 11: Under dispenser containment (UDC) was required

for all UST systems by

CORRECT ANSWER: December 31 2003

Question 12: System for exchanging gas vapors in a storage tank

and product in a fuel delivery truck

CORRECT ANSWER : Stage 1 vapor recovery

Question 13: An approved method for non visual monitoring for

existing UST systems.

CORRECT ANSWER : Statistical Inventory Reconciliation

(SIR)

Question 14: ATG must be capable for detecting a release of ?

CORRECT ANSWER : .2 gallons per hour

Question 15: Manual inventory reconciliation.

CORRECT ANSWER : No longer an approved method for non

visual monitoring on existing UST systems

  • | Page

Question 16: Automatic line leak detectors installed on

underground piping with secondary containment shall be capable of tetecting a leak of ?

CORRECT ANSWER : 3 gallons per hour at 10 psi

Question 17: ATG should be programmed to test the tank ?

CORRECT ANSWER : At least monthly

Question 18: According to PEI RP 300 a combustible gas can be

used to ?

CORRECT ANSWER : Detect vapor leaks in a vapor recovery

system.

Question 19: According to PEI RP 300. A written scope of work

for vapor recovery installation should include?

CORRECT ANSWER : Construction plans

Question 20: Positive shut off overfill protection device must

stop the flow of fuel when the tank is no more then ?

CORRECT ANSWER : 95% full

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Study Guides
Added: Aug 14, 2025
Description:

CALIFORNIA UST SERVICE TECHNICIAN PART 1 QUESTIONS AND ANSWERS Question 1: July 1 2005, service techs shall possess or work under someone who has a current certification indicating he or she has pa...

Get this document $30.00