Con 3990 Exam Q & A Prep
Acceptance constitutes acknowledgment that the supplies or services?
Correct Answer:
Conforms with applicable contract quality and quantity requirements
The contract shall or shall not specify the place of acceptance?
Correct Answer:
Shall
Certificate of conformance maybe used in certain sentences at the discretion of the CO, what are they?
Correct Answer:
-acceptance on the basis of contract or certification of performance is in the governments interest -small losses would be incurred in the event of a defect or; -contractors reputation or past performance constitutes it
Acceptance constitutes acknowledgment that supplies or services performed with a book or contract quality and quantity requirements, except a subject to other terms and conditions of the contract. True or false
Correct Answer:
True
- / 4
Supplies accepted at a place to other than _______ Shall not be re-inspected at the definition for acceptance purposes, but should be examined at the destination for quantity, damaged in transit, impossible substitution or fraud.
Correct Answer:
Destination
Title To supplies shall or shall not pass to the government up on formal acceptance, regardless of when or where the government takes physical possession, unless the contract specifically provides for earlier passage of the title
Correct Answer:
Shall
Title to supplies shall pass to the Government upon form acceptance, regardless of when or whatever it takes his opposition, unless the contracts basically rods for other passage. True false
Correct Answer:
True
If the CEO determines that any failure to perform results from one or more of the [excusable delays],the delivery schedule shall be...
Correct Answer:
Be revised, subject to the words of the government under the termination clause of the contract
- / 4
Except for defaults of subcontracts at any tier, the contractor shall not be end of all because of any failure to perform the contract under its terms if the failure arises from causes beyond the control and without the fault or negligence of the contractor. True or false
Correct Answer:
True
What are examples of excusable delays?
Correct Answer:
-Act of God or of the public enemy -Acts of the government and either it's sovereign or contractual capacity -fires -floods -epidemics -quarantine restrictions -strikes -freight embargoes -unusually severe weather
There are two types of warranties: Implied and express warranties. True or
False
Correct Answer:
True
- / 4
When drafting solicitation contracts, contacting officers must under five for each line item number, sub line item number, or exhibit line item number the applicable payment clauses that apply to each item when the solicitation contract contains items that will be subject to different payment terms. True or false
Correct Answer:
True
What type of contraction is used to make administrative changes?
Correct Answer:
Unilateral
What type of contraction is used to definitive letter contracts?
Correct Answer:
Bilateral
What type of contraction is used to issue termination notices?
Correct Answer:
Unilateral
What type of contraction is used to make negotiated equitable adjustments resulting from the issuance of a change order.
Correct Answer:
Bilateral