CON 3990V EXAM PREP
QUESTIONS AND ANSWERS
When should all other (not SAP, FFP, or indirect cost rate) contract files be closed?
- Within 6 months of the month the KO receives evidence of physical
- Within 12 months of the month the KO receives evidence of physical
- Within 20 months of the month the KO receives evidence of physical
- Within 36 months of the month the KO receives evidence of physical
completion
completion
completion
completion
Correct Answer: C) Within 20 months of the month the KO receives evidence of
physical completion
When is a contract considered physically complete?
- When final payment has been processed and dispersed to the contractor
- When the warranty period expires and all disputes are settled
- When the contractor has completed required deliveries/services, the Gov has
- When the Contracting Officer formally issues the final performance review
accepted them, and option provisions have expired, or a notice of termination is given
Correct Answer: C) When the contractor has completed required
deliveries/services, the Gov has accepted them, and option provisions have expired, or a notice of termination is given
- | P a g e
What are the steps to close out a contract file?
- 1) KTR submits final invoice 2) KO signs it 3) File is sent to archives
- 1) Contract admin office initiates and deobligates excess funds 2) KO issues
- 1) KO creates D&F 2) Funds are obligated 3) Contract is closed manually in
- 1) Defense Contract Audit Agency (DCAA) audits file 2) Legal reviews 3)
completion statement 3) KO files statement and sends signed copy to admin office
FPDS
KO signs closure
Correct Answer: B) 1) Contract admin office initiates and deobligates excess
funds 2) KO issues completion statement 3) KO files statement and sends signed copy to admin office
How long are contract documents retained after closeout?
- 3 years after final payment
- 5 years after final payment
- 6 years after final payment
- 10 years after final payment
Correct Answer: C) 6 years after final payment
What does a KO need prior to commencement of negotiations for a sole source contract, unsolicited proposal, or award without full and open competition?
- Determination and Findings (D&F)
- Source Selection Plan
- Independent Government Estimate (IGE)
- Justification and Approval (J&A) which justifies actions in writing, certifies
accuracy, and obtains required approval
- | P a g e
Correct Answer: D) Justification and Approval (J&A) which justifies actions in writing, certifies accuracy, and obtains required approval
The KO shall not award a sole-source contract for an amount exceeding $25M
unless:
- They have a signed Determination and Findings
- They have a signed Justification and Approval
- They have received Congressional approval
- They have received at least two bids
Correct Answer: B) They have a signed Justification and Approval
Which of the following should a Justification & Approval (J&A) include?
- Description of action, estimated value, statutory authority, rationale for
- An independent government estimate, the draft contract, and source selection
- The contractor's financial statements and technical capability reports
- The names of all competitors in the industry and a risk mitigation plan
specific KTR, market research, and KO certification
plan
Correct Answer: A) Description of action, estimated value, statutory authority,
rationale for specific KTR, market research, and KO certification
What are the thresholds for J&A approval?
- Under $250k - KO; Over $250k - HCA
- Under $1M - KO; Over $1M - SPE
- Under $750k - KO; Over $750k and under $100M - HCA; Over $100M -
- Under $5M - KO; Over $5M - Agency Head
Senior Procurement Executive (SPE)
- | P a g e
Correct Answer: C) Under $750k - KO; Over $750k and under $100M - HCA;
Over $100M - Senior Procurement Executive (SPE)
Who develops a solicitation?
- The Contractor and the Seller
- The Government & The Buyer
- The End User exclusively
- The Source Selection Authority
Correct Answer: B) The Government & The Buyer
Who prepares an offer?
- The Government and the Buyer
- The Contracting Officer
- The Source Selection Evaluation Board
- The Contractor and the Seller
Correct Answer: D) The Contractor and the Seller
During the post-award phase while the contract is being performed, who has responsibility for quality?
- The Contracting Officer
- The Defense Contract Management Agency (DCMA)
- The Seller
- The End User
Correct Answer: C) The Seller
What does the award phase involve?
- Only work performed by the Government