CPPB Prep D.N. Questions with 100% Verified Correct Answers-2024
If considering contract termination, the agency should first:
- Take punitive action against the contractor.
- Stop accepting delivered products or services offered by the contractor.
- Start a file that documents the conflicts.
- Notify the authorities. - Correct Answer C. Start a file that documents the conflicts
- Done correctly, will result in a lower acquisition price.
- Is synonymous with the total cost of ownership.
- Includes operating and maintenance costs but does not reflect disposal costs.
- Focuses on maintenance costs. - Correct Answer
Some agencies provide monetary assistance to qualified citizens by the use of smart cards. What is a smart card and how does it work? - Correct Answer Which is a true statement about Life Cycle Costing?
A solicitation document currently on the street contains a clause that has been revised by an addendum, which then turns out to be incorrect.What happens if the bid opening date hasn't occurred yet?What happens if the bids have not been opened? - Correct Answer Failure of a bidder to return the number of signed copies requested, failure of a bidder to acknowledge receipt of an addendum or failure to execute a required certificate are often considered:
- Deal-breakers 1 / 2
- Responsiveness issues
- Minor irregularities
- Major irregularities - Correct Answer Minor irregularites
- Termination for Default
- Issuance of a Cure Notice
- Termination for Convenience
- Issuance of a Notice of Suspension - Correct Answer Termination for Convenience
- Assume that the proposed milestones are too aggressive.
- Ask the contractor if he can meet the proposed milestones.
- Offer to change the milestones.
- / 2
You've opened some bids and identified the lowest responsive/responsible bidder. However, due to internal issues in the using department, several months have passed without the award being made.Before pressing on, what action, if any, should be taken with the low bidder? - Correct Answer Making sure that the pricing has not changed.A county has a multi-year contract to provide land use planning services for a forthcoming park renovation. Due to a severe funding shortage, all non-critical services have been put on hold for a year (at the earliest). The county has decided to cancel the contract and re-solicit the services when funding is available. Which of the following is the best cancellation method?
What's the difference between a protest and a dispute? - Correct Answer A protest challenges the award or proposed award of a contract.The dispute is an issue or disagreement with the contracting officer that arises after you have won and been awarded a contract.In a negotiation meeting, you notice that the contractor's proposed project manager starts to frown each time the topic of milestones is talked about. What should you do?