Question : In the absence of specific requirements in the

governing design standard , at the option of the engineer what other standards shall the contractor be certified too ?If no standard is required what shall the contractor prove ?

Correct answer: W47.1

The contractor must prove their compentency to the engineer.

Question : What processes are covered by this standard ?

Correct answer: SMAW, GMAW, MCAW, FCAW,

SAW, ESW, EGW, SW

Question : Filler metals and allied materials are classified

under what standard ?

Correct answer: CSA W48

  • | Page

Question : What processes filler metals and other

materials not covered under CSA W48?

Correct answer: Stud welding is not covered under CSA

W48. It shall conform to the requirements of clause

3.1.2.2

Question : Any welding process not covered by CSA

W59 or not written into this standard shall be covered under the acceptance criteria of what other standard ?

Correct answer: CSA W47.1

Question : What processes are deemed pre qualified as

long as they conform to what clause ? And therefore are approved for use with out joint welding qualification providing that welding procedures also conform to clause

4,5,10

Correct answer: SMAW, SAW, FCAW, MCAW (spray

transfer) and GMAW (spray transfer) as long as they conform to clause 10 shall be deemed as prequalified .

  • | Page

Question : Steel base metal to be welded under this

standard shall conform to what standard?

*equivalent welding quality shall be established on the basis of composition and carbon equivalent

Correct answer: Steel material to be welded should

conform to CSA or ASTM requirements

Question : What CSA standard shall steel base metal that

is to be welded conform to ?

Correct answer: CSA G40.21

Question : Welded structures should be designed to

permit what ? during construction

Correct answer: adequate accessibility

Question : Inspection requirements should be defined

where ?

Correct answer: On the plans or in the specifications

  • | Page

Question : In the case of partial joint penetration groove

welds. where shall it specify the effective throat ?

Correct answer: The design drawing shall specify the

required effective throat

Usually the weld symbol will dictate this by showing (CJP) or (PJP) in the weld symbol notes

Question : What is the definition for CJP

Correct answer: Complete joint penetration

Question : What is the definition of PJP

Correct answer: partial joint penetration

Question : Define a flare groove weld

Correct answer: A flare grove is when one or both sides if

the joint to be welded has a radiused edge.

Question : What must be done when corners of slots are

provided for fillet welding ?

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Study Guides
Added: Aug 18, 2025
Description:

CSA W59 WELDING INSPECTOR LEVEL 1 QUESTIONS & ANSWERS | 100% CORRECT | VERIFIED Question : In the absence of specific requirements in the governing design standard , at the option of the engineer w...

Get this document $30.00