OSCM 373 - Exam 2 Latest Update 2025-2026 Questions and 100% Verified Correct Answers Guaranteed A+
A company wishes to design a repetitive process. The manager knows that making a product takes (at a minimum) 5 minutes and estimates they will have to make 120 units every hour. What is the minimum number of workstation required?
- 60
- 20
C. 120
D. 10 -CORRECT ANSWER: D. 10
A highly specialized product needed in a very low volume, based on an individual order, would utilize which manufacturing process?
- Mass Customization
- Mass Production
- Continuous
- Job Shop
- Repetitive
F. Hybrid -CORRECT ANSWER: D. Job Shop
A layout in which the product or project remains stationary, and workers, materials, and
equipment are moved as needed is a:
- Process Layout
- Fixed Position Layout 1 / 2
- Combination Layout
D. Service Layout -CORRECT ANSWER: B. Fixed Position Layout
A machine has a design capacity of 5,000 and an effective capacity of 4,000 units per year. If the expects output is 3,000 per year, what would be the Utilization?
A. 100%
B. 50%
C. 60%
D. 80% -CORRECT ANSWER: C. 60% (3000/5000=0.6)
A process has a fixed cost of $20,000, variable costs per unit of $10 and outputs can be sold for $15 per unit.What is the Break-Even Point?
- 2,000 units
- 4,000 units
- 800 units
D. 1,000 units -CORRECT ANSWER: B. 4,000 units
20,000(15-10)=4,000
A product that depends on several processes for its creation would utilize which manufacturing process?
- Repetitive
- Job Shop
- Mass Customization
- Hybrid