Florida Contractors Manual Questions and Answers – 1 Latest Update 2024-2025 Actual Exam Questions and 100% Verified Correct Answers Guaranteed A+
___ days so the maximum time after commencing construction for the contractor to give notice to the owner of his lien rights
A-30 B-45 C-60
D-90 - CORRECT ANSWER: B-45
A contract will not be enforced if it is
A- oral B- illegal C- no work is accomplished for 90 days
D- all of the above - CORRECT ANSWER: B- illegal
A lien that is properly perfected may be discharged by any of the following except ____
A-the completion of the project B-by failure to begin action to enforce writhing prescribed time limit C-by an order of the circuit court D-by recording in clerks officer of a judgement by court of competent jurisdiction - CORRECT ANSWER: A- the completion of the project
A secondary qualifying agent has pulled a permit for a building project. There is a problem with payment to a subcontractor. ___ is responsible for the payment to the subcontractor 1 / 3
A-primary qualifying agent B-both primary & secondary have joint responsibility C-secondary qualifier
D-owner of the company - CORRECT ANSWER: A- primary qualifying agent
A short-term project schedule is a detailed explanation of the next two weeks of construction activities and should be developed and/or reviewed by all of the following except ___
A-superintendent B-architect C-subcontractors
D-project engineer - CORRECT ANSWER: B- architect
A subcontractor started work in his co tract with the general contractor on aug. 1 2021. The owner made the final payment to the general contractor on sep 13 2021. The latest fat the sub contractor can serve notice to owner to preserve his claim under the construction kein law is _______ 2021
A- sep 16 B- sep 15 C- sep 13
D- sep 12 - CORRECT ANSWER: D- sep 12
Page: 9-21
According to the statue of frauds, a contract need not be in writing and still be enforceable in Florida if less than ___ and ___
A-$500 in value and less than 2 years in length B-$1000 in value and less than 1 year in length 2 / 3
C-$2500 in value and less than 1 year in length D-$500 in value and less than 1 year in length - CORRECT ANSWER: D-$500 I'm value and less than 1 year in length
After relocating his business to a new location, the contractor has ___ days to notify the department of his new address
A-10 B-21 C-45
D-60 - CORRECT ANSWER: C-45
All of the following must follow OSHA standards except ___
A-religious establishments B-general contractor with one employee C-landscape contractors
D-equipment rental business - CORRECT ANSWER: A-religious establishemnts
An Action for breach of a written contract must be brought within ____ years
A-2 B-3 C-4
D-5 - CORRECT ANSWER: D-5
Based on the completed contract method, for a job bid at $300,000 and currently 66.67% complete, with a gross profit of 16.67% (50,000) the current amount of profit recognized would be
A-$200,000
- / 3