DBIA EXAM 2 QUESTIONS WITH CERTIFIED
ANSWERS LATEST 202 4 BEST SOLUTION
Which project delivery for Fast food franchise:
-new facility
- standard design
- prescriptive specs
Design-Bid-Build best for this one.Process industry. rebuild after fire, upgrade facility, market timing critical***
project delivery for fastest design and construction?:
DESIGN-BUILD
Owner new to D&C, owner heavily involved, wants price competition, wants GMP before construction commitment CMAR: Construction Management at Risk. A/R still works for the owner. Can compete packages to the subtrades. If owner can't get to GMP, can complete the design and bid as typically would.Characteristics of Design-Build
- completion time critical
- performance-based requirements
- collaboration important (co-location, less delays claims and disputes)
- flexibility of approach (alternatives will be presented to meet performance)
- prescriptive specs (owner controls details)
- lowest initial price most important (low-bid) 1 / 4
Characteristics of Design-Bid-Build
- schedule less important
- prescriptive specs
- early constructor/contractor involvement (pre-qualified subs) pre-con
- earlier knowledge of cost than D-Bid-B
- typically faster than D-Bid-B
- QBS
- involved in pre-design
- parameters, not solutions
- budget disclosed
- Characteristics of CMAR
Design Build (progressive)
Criteria for Design-Build
-performance based
RFP where design is 20+% developed bridging document RFP where design is 35+% Draw-Build (focus on price) RFP w 5-20% design best practice, mostly performance based Quals-based to price based Developer-led PPP and transportation 2 / 4
typically hires a design-build team Integrated Project Delivery Tri-party contract. not often in public sector Progressive Design Build
- typically QBS
- GMP developed later
- key trade partners brought on later
- what if the owner and db cannot agree? what does the off-ramp look like?
- not traditional A/E contracts
- not traditional construction contracts
- typically lump sum AND Best Value (negotiated)
- Early Involvement
- Qualifications-Based Selection
- Cost Transparency
- Fostering Environment of Trust
Distinguishing Characteristic of Design-Build ONE contractual relationship. At D-B-B and CMAR, Owner has two contract: separate contracts with A/E and Contractor What's unique about Design-Build contract?
Key factors in DB team alignment
Integration & Collaboration
How and when team is formulated:
- How are key trade partners selected: Quals vs low bid 3 / 4
- When are they selected:
Early- During proposal development (not waiting for buy-out Owners Role
- Define Value in the RFP
- disclose the budget (not a range)
- Provide supportive and collaborative environment with a sense of urgency (benefit is
- be accessible - stay continuously engaged, especially early on
- make timely decisions (not a micro-manager...nor missing in action)
- Project Definition (pre-award, translate Owner's needs into terms that can be
to obtain and early lump sum)
Owner Rep Role
understood by DB teams to submit proposals
- Post-award, CM agency services: solution will be performance based
Essential Owner's Rep Skills
- technical
- leadership
- communication
- facilitative
- common understanding
- trust
- early trade partner engagement
- / 4
Successful Teaming
-shared motivations & incentives Teaming Agreements