Occurs when the design component has been priced and confirmed "within budget" and when the drawings and specs are approved by the Designer on record as complying with the RFP. - ANSWER✔✔Committed Design

  • - Facilitate decisions to keep the estimate from increasing budget.
  • - Encouraging proactive approaches to resolve changes quickly with the owner.
  • - Tracking & Documenting cost fluctuations between milestone estimates.
  • - Mitigating disputes before they get larger. - ANSWER✔✔Trend Management
  • When the design is completed enough such that accurate cost estimates can be determined. - ANSWER✔✔Design Stability A multi-disciplined comprehensive risk identification, evaluation and analysis session that involves representatives from the entire design build team. - ANSWER✔✔Joint Risk Assessment Award Fees, Shared Shavings, Target Cost Contracts, Alliance Contracts. - ANSWER✔✔Performance Incentives Cooperative Contracting model that is characterized by collaboration and aligning values, goals and objectives amongst owner, architect and contractor. Shares Risk among all participants. - ANSWER✔✔Alliance Contract Incentive mechanism for target cost contracts that triggers a financial reward when the DB'er meets or exceeds certain performance standards. Typically for non-cost related performance items: safety, schedule, communication, customer satisfaction. - ANSWER✔✔Award Fee 1 / 2

  • - ID MWEBE Goals
  • - Expected Substantial Completion Date
  • -Weighted proposal selection criteria

4 - Performance Requirements - ANSWER✔✔RFP should include:

  • - Statement of desired results
  • - Attributes or Characteristics of a facility Element
  • - Measurable or observable definitions of performance
  • - Testing requirements to validate performance - ANSWER✔✔Performance Specs should include:
  • Form of Procurement where techinical proposals are critiqued not scored and the proposer revises design and is then judged off of low bid. - ANSWER✔✔Equivalent Design/Low Bid AKA BAFO

  • - Fixed Price/Best Design
  • - Equivalent Design/Low Bid
  • - Adjusted Low Bid - ANSWER✔✔Best Value Procurement Examples
  • - When the owner issues addenda to the RFP after reviewing design proposals to reflect aspects that
  • the owner likes about each proposal. - ANSWER✔✔Technical Leveling

  • - Footprint SF
  • - Gross SF
  • - Building Perimeter

4 - Roof Area - ANSWER✔✔Conceptual Estimate needs:

Programming and design are developed by the design-build entity. - ANSWER✔✔Direct Design-Build

  • / 2

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: EXAM ELABORATIONS
Added: Aug 29, 2025
Description:

DBIA - PRINCIPLES OF DESIGN-BUILD AND POST AWARD 2024 ACTUAL EXAM QUESTION AND CORRECT ANSWERS VERIFIED ANSWERS ALREADY GRADED A+ Occurs when the design component has been priced and confirmed "wit...

Get this document $30.00