GENERAL CRANE SAFETY EXAM 2024-2025

COMPLETE 150 ACTUAL EXAM QUESTIONS AND

CORRECT DETAILED ANSWERS (VERIFIED ANSWERS)

GRADED A+

The crane operator STOPS the crane whenever _____is in question.

  • the lift
  • conditions
  • safety
  • the union contract - Correct Answer - C) safety

When taking any medications that can affect a person's capability to think, reason, or react in normal situations, the operator should do which of the following?

  • Operate more cautiously.
  • Report it to his or her supervisor.
  • Stay at home.
  • See how he or she feels driving to work.
  • Nothing. It is a personal thing. - Correct Answer - C) Stay at home.

What types of power does a Category 1 or 4 crane generally use, and what is its source?

  • Electric or hydraulic power supplied by a diesel engine
  • Pneumatic and hydraulic power supplied by a compressor
  • Hydraulic and water power supplied by a compressor
  • Pneumatic and electric power supplied by a backup generator - Correct Answer - A)
  • Electric or hydraulic power supplied by a diesel engine

  • / 4

pg. 2 The formula for determining the area of a triangular shaped object is-

  • Base x Height divided by 2
  • Base x Height × 2
  • Length x Width x Height
  • None of the above - Correct Answer - A) Base x Height divided by 2

Components that support the load and upon failure would cause dropping or uncontrolled lowering of the load are

  • alterations and/or modifications
  • general safety devices
  • load controlling parts
  • operational safety devices
  • load bearing parts - Correct Answer - E) load bearing parts

When making personnel lifts, the capacity of a mobile crane for a given radius is reduced by-

A) 25%

B) 50%

C) 75%

D) 80%

  • 100% - Correct Answer - B) 50%

What should an operator do if he or she is not sure of the meaning of a signal?

  • Place the load in a safe area
  • Keep operating as long as he or she can see the load
  • Stop operation until the meaning of the signal is understood
  • Guess at what the signal means until the Rigger signals to stop operations - Correct
  • Answer - C) Stop operation until the meaning of the signal is understood

  • / 4

pg. 3

Which of the following can affect the crane's capacity?

  • Out of level
  • Outrigger position
  • Side loading
  • Load swing
  • Any of the listed factors above - Correct Answer - E) Any of the listed factors above

If an object is 6 feet long, 4 feet wide, and 2 inches thick, what is the area of the object?

  • 4 square feet
  • 4 cubic feet
  • 24 square feet
  • 24 cubic feet
  • 48 square feet - Correct Answer - C) 24 square feet

New shackles put into the weight handling equipment program are required to have all of the following markings EXCEPT-

  • Date of manufacture
  • Rated load
  • Manufacturer name, logo, or trademark - Correct Answer - C) Manufacturer name,
  • logo, or trademark

Manufacturer's load rating charts for cranes must be-

  • Posted outside the cab
  • Visible to the Crane Rigger
  • Available from the engineering department
  • Available from the supervisor
  • Visible to the operator - Correct Answer - E) Visible to the operator
  • / 4

pg. 4 Why should crane swing be relatively slow?

  • so that the crane can be operated for longer periods
  • to prevent outward swing of the load due to centrifugal force
  • to keep the operator from having to correct misalignment
  • to prevent the load from falling out of the rigging gear - Correct Answer - B) to
  • prevent outward swing of the load due to centrifugal force

A commercial truck mounted crane with a capacity of 14,000 pounds is a______crane.

  • Category 1
  • Category 2
  • Category 3
  • Category 4 - Correct Answer - D) Category 4

What is the definition of "boom length"?

  • the distance from the boom "heel" or "foot" pins to the jib attachment pins
  • the distance from the rotate base to the center of the boom tip sheave
  • the distance from the center of rotation on the crane to the center of the boom tip
  • sheave

  • the distance from the boom "heel" or "foot" pins to the center of the boom tip sheave
  • Correct Answer - D) the distance from the boom "heel" or "foot" pins to the center of
  • the boom tip sheave

On cranes, lowering the boom with the hook blocks raised will most likely result in

  • tipping
  • two-blocking
  • overloading
  • insufficient hook height
  • none of the above - Correct Answer - B) two-blocking

Is it necessary for the operator to see the load or work area?

  • / 4

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: EXAM ELABORATIONS
Added: Aug 28, 2025
Description:

pg. 1 GENERAL CRANE SAFETY EXAM 2024-2025 COMPLETE 150 ACTUAL EXAM QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) GRADED A+ The crane operator STOPS the crane whenever _____is in questio...

Get this document $30.00