According to the IBC, the "blank" is to hire the special inspector. - Answer-owner or owners agent. 2009 IBC Section 1704.1

According to the IBC, the "blank" is the responsible for the approval of a person's qualifications to act as a special inspector. - Answer-code official. 2009 IBC, Section 1704.1

According to the IBC, discrepancy corrections are made

known to the building official by: - Answer-final report.

2009 IBC, Section1704.1.2

When is the code official to be made aware of a discrepancy found during a special inspection? - Answer-If it is not corrected by the contractor. 2009 IBC, Section

1704.1.2

  • / 4
  • | P a g e

According to the Model Program for Special Inspection, the special inspector is to document work that is

nonconforming: - Answer-In a written report - Section II B

  • - Model Programs

According to the Model Program for Special Inspection, the special inspector is to prepare written report of

inspection: - Answer-After each inspection visit - Section II

B 5 - Model Programs

According to the Model Program for Special Inspection, which of the following items does not need to be included in each inspection report? - Answer-Description of discussions with the contractor - Section B 5 - Model Programs

According to the Specification for Structural Joints using high strength bolts, the nominal diameter of standard bolt holes shall be how much larger than the nominal bolt diameter? - Answer-1/16 inch - Specification for Structural Joints Table 3.1

  • / 4
  • | P a g e

Discrepancies in the work shall be brought to the immediate attention of the "blank" for corrective action. - Answer-the contractor - 2009 IBC, Section 1704.1.2.

The special inspector shall furnish inspection reports to the "blank" and to the "blank"? - Answer-Building Official and Registered Design professional

The special inspector shall provide continuos inspection

of: - Answer-Single-pass fillet welds greater than 5/16 inch

in size - 2099 IBC, Table 1704.3, Item 5.3

The special inspections required by this code are not required where the work is done on the premise of a? - Answer-Approved fabricator - 2009 IBC, Section 1704.2.2

The special inspection of the steel fabrication process shall not be required where the fabricator does not perform any? - Answer-heating operations - 2009 IBC, Section 1704.3, Exceptions # 1

According to the Specifications for Structural Steel Buildings, ASTM Standard "blank" is to be used for the 3 / 4

  • | P a g e

material test for steel sheets. - Answer-A568 - Section A31, Specifications for Structural Steel Buildings

According to the Specifications for Structural Steel Buildings, the "blank" conducts the material tests for identification of the structural steel. - Answer-Fabricator or Testing Laboratory - Section A31, Specifications for Structural Steel Buildings.

According to the Specifications for Structural Steel Buildings, which of the following steel members are allowed to be unidentified steel? - Answer-Unimportant members, where their physical properties and weldability would not affect the structure strength - Section A31b, Specifications for Structural Steel Buildings

According to the Code of Standard Practice for Steel Buildings and Bridges, how is steel of special material to be identified? - Answer-It is marked by the supplier - Section 5.1.1, Code of Standard Practice for Steel Buildings and Bridges

According to the Code of Standard Practice for Steel Buildings and Bridges, how are fabricators stock steel

  • / 4

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: EXAM ELABORATIONS
Added: Sep 4, 2025
Description:

ICC BOLTING TEST FINAL EXAM 2025 CURRENTLY TESTING COMPLETE EXAM QUESTIONS WITH DETAILED VERIFIED ANSWERS (100% CORRECT ANSWERS) /ALREADY GRADED A+ / LATEST EXAM!!! According to the IBC, the "blank...

Get this document $30.00