pg. 1 WGU C176 Business of IT Pre-Assessment Latest 2024 Complete 200 Actual Exam Questions with Correct Verified Answers/ Rated A+
A key responsibility of the project manager includes informing this person of changes, status, conflicts, and issues on the project.A The project coordinator B The project sponsor C The project requestor D The most influential project stakeholder - Correct Answer - The project sponsor
Jack is a key stakeholder on the project. He's a big believer in the benefits of the project and provides enthusiasm, energy, communication, and motivation for your project. What is Jack's role?A Project stakeholder B Project champion C Project team member D Business analyst - Correct Answer - Project champion
Which stakeholder assigns employees to the project in the matrix organization?A Functional manager B Project manager C Sponsor D Customer - Correct Answer - Functional manager 1 / 4
pg. 2
Which of the following does a PMO provide? Choose three.A Templates B Change control C Governance process D Tools E Business case F High-level scope definition - Correct Answer - Templates Governance process Tools
The governance processes for project management are well established in your organization. Who established these processes?A Project manager B Sponsor C PMO D Project team - Correct Answer - PMO
This component of the project request describes the project objectives, the high-level deliverables, and the reason for the project.A High-level goals and objectives definition B High-level scope definition C High-level deliverables definition D Project request justification - Correct Answer - High-level scope definition
Your project team members and key stakeholders are confused about the project you are all working on. What is the most compelling reason for this?A The project sponsor has not signed the project request authorizing it to begin.B The business case is not well documented. 2 / 4
pg. 3 C The project team members don't understand their roles and responsibilities. - Correct Answer - The business case is not well documented.
Which of the following is not true for the critical path?A It's the shortest activity sequence in the network.B You can determine which tasks can start late without impacting the project end date.C It controls the project finish date.D It has zero float. - Correct Answer - It's the shortest activity sequence in the network.
Starting two activities at the same time that were previously scheduled to start sequentially is known as which of the following?A Crashing B Baselining C Fast tracking D Mandatory dependency - Correct Answer - Fast tracking
What are the most commonly used forms to display project schedules? Choose two.A A spreadsheet B CPM diagrams C Gantt charts D PERT charts - Correct Answer - Gantt charts PERT charts
What are the crashing and fast tracking techniques used for?A Activity sequencing B Precedence diagramming C Task definition D Duration compression - Correct Answer - Duration compression
- / 4
pg. 4 You have added a checkpoint in the project schedule to determine whether the work is accurate. What is this called?A Checkpoint gate B Approval gate C Quality gate D Governance gate - Correct Answer - Quality gate
Which of the following is true for float?A It's calculated by adding the durations of all tasks and dividing by the number of tasks.B It is calculated only on the longest path of the project schedule.C It's the amount of time an activity can be delayed without delaying the project completion date.D It's time that you add to the project schedule to provide a buffer or contingency. - Correct Answer - It's the amount of time an activity can be delayed without delaying the project completion date.
You are a project manager for a major movie studio. You need to schedule a shoot in Denver during ski season. This is an example of which of the following?A External dependency B Finish-to-start relationship C Mandatory dependency D Discretionary dependency - Correct Answer - External dependency
Your project is underway and your team members are working well together, anticipating the needs of the project, and they all understand their roles in the project. A new team member has been introduced and started working with the team this week. Which stage of team development does this situation represent?A Storming B Forming C Norming D Performing - Correct Answer - Forming