- | P a g e
NCIDQ IDPX PREP EXAM NEWEST 2024
ACTUAL EXAM COMPLETE 50 QUESTIONS
AND CORRECT ANSWERS (VERIFIED
ANSWERS) |ALREADY GRADED A+||BRAND
NEW VERSION!!
What portion of a contract typically outlines the designer's responsibilities to the client?
- Scope of services
- Project description
- Terms and conditions
- Compensation schedule - CORRECT ANSWER -A.
Scope of services
In which space is emergency lighting REQUIRED?
- Elevators
- Private offices
- Egress corridors 1 / 4
- | P a g e
- Restrooms - CORRECT ANSWER -The correct answer is C.
Emergency lighting is required at all exits and passageways leading to an exit when a building is in use.
P2 Codes and Standards
Why is it necessary to indicate the placement of the proposed elevator and stairway in a preliminary plan?
- To ensure an acceptable location to meet all codes
- To verify the client's budget constraints
- To establish the structural support work required
- To ensure accessibility and visibility to visitors - CORRECT
ANSWER-A.
To ensure an acceptable location to meet all codes
Which on-site installation should be completed BEFORE painting the walls?
- Rubber base
- Grid lighting
- Receptacle covers 2 / 4
- | P a g e
- VCT tile - CORRECT ANSWER -The correct answer is B.
Electrical work, such as the installation of light fixtures, should occur before surface finishes are applied. Flooring is typically installed last.
P3 Building Systems and Integration
To promote effective project decision-making at weekly job meetings, who should attend the meetings?
- Senior management of the client company, construction
- Senior management of the client company, construction
- Client representative, design project manager, consulting
- Client representative, construction project manager, design
project manager, design project manager, and consulting engineers
project manager, design project manager, consulting engineers, and foremen from critical trades
engineers, and foremen from critical trades
project manager, and foremen from critical trades - CORRECT ANSWER-The correct answer is D. The design team typically includes the interior designer, the client, the general contractor, and several subcontractors or their designated representatives
P6 Contract Administration 3 / 4
- | P a g e
New construction requires which MINIMUM width for a standard, accessible side transfer in a public restroom?
- 48" [1200 mm]
- 54" [1370 mm]
- 60" [1500 mm]
- 66" [1670 mm] - CORRECT ANSWER -The correct answer
is C. This measurement accommodates the turning circle required by wheelchairs to be unobstructed.
P2 Codes and Standards
During construction, the client wishes to make a change in the shape of a drywall bulkhead. How should the request be communicated?
- Designer informs the drywall subcontractor.
- Client informs the general contractor.
- Drywall subcontractor informs the general contractor, who
- Client informs the designer, who informs the general
- / 4
informs the designer.
contractor - CORRECT ANSWER -The correct answer is D.