- Which Nevada agency is responsible for issuing a General Engineering (A) contractor’s
- Nevada Department of Transportation (NDOT)
- Nevada State Contractors Board (NSCB) [ANSWER]
- Nevada State Board of Engineers
- Nevada Department of Business & Industry
license?
Rationale: The NSCB regulates contractor licensing in Nevada, including Class A General Engineering licenses.
- The Nevada State Contractors Board can discipline a contractor for all the following
EXCEPT:
- Abandonment of a construction project
- Diversion of project funds
- Failure to maintain required insurance
- Hiring a subcontractor without a written contract [ANSWER]
Rationale: Written contracts with subcontractors are recommended but not legally required in all cases; the other actions are disciplinary violations under Nevada law.
- What is the primary focus of a Nevada General Engineering (A) license classification?
- Residential building
- Specialty trades like painting and flooring
- Large-scale infrastructure such as highways, bridges, and utilities [ANSWER]
- Commercial tenant improvements
Rationale: The “A” General Engineering license covers projects like highways, tunnels, dams, and utilities, not residential or small-scale commercial work.
- A licensed General Engineering contractor in Nevada must renew their license every:
- 6 months
- 1 year 1 / 4
- 2 years [ANSWER]
- 5 years
Rationale: Nevada contractor licenses are renewed biennially (every two years) provided fees and continuing obligations are met.
- Which bond is required before a contractor can legally operate in Nevada?
- Bid bond
- Performance bond
- Contractor’s license bond [ANSWER]
- Payment bond
Rationale: All Nevada licensed contractors must file a contractor’s license bond or cash deposit with the NSCB as a condition of licensure.
- What is the maximum fine per violation the NSCB may impose on a contractor?
A. $1,000
B. $5,000
C. $25,000
D. $50,000 [ANSWER]
Rationale: The NSCB has authority to fine contractors up to $50,000 per violation, depending on the severity.
- Which document must be kept on the jobsite at all times for inspection in Nevada?
- Contractor’s business license
- Building permit [ANSWER]
- Subcontractor agreements
- Surety bond certificate
Rationale: Building permits issued by the local jurisdiction must be posted and available for inspection on the jobsite.
8. When bidding public works projects in Nevada, contractors must comply with:
- Federal OSHA only
- Nevada Prevailing Wage laws [ANSWER]
- Residential construction codes only
- HOA governing documents 2 / 4
Rationale: Public works projects in Nevada require payment of prevailing wages to workers as established by the state.
9. A contractor who operates without a Nevada license may be charged with:
- Civil infraction only
- Misdemeanor criminal offense [ANSWER]
- Felony offense
- Business code violation only
Rationale: Contracting without a valid Nevada license is a misdemeanor, subject to fines and potential jail time.
- The general engineering classification typically does NOT cover which of the following?
- Bridges
- Highways
- Dams
- Single-family homes [ANSWER]
Rationale: Class A General Engineering covers infrastructure projects; single-family residential falls under the “B” General Building license instead.
Questions 11–60
11. Before starting excavation work in Nevada, contractors must notify:
- The Nevada State Contractors Board
- The local building inspector
- Underground Service Alert (USA) 811 [ANSWER]
D. OSHA
Rationale: Nevada law requires a “Call Before You Dig” (811) notification before excavation to protect underground utilities.
- Which of the following is a requirement for a Responsible Managing Employee (RME)
- Must be at least 18 years old
- Must have at least 4 years of verifiable experience in the trade [ANSWER] 3 / 4
in Nevada?
- Must be a licensed civil engineer
- Must be a Nevada resident
Rationale: RMEs need at least 4 years of practical experience in the field; residency is not a requirement.
- If a contractor’s license is revoked, the licensee may apply for reinstatement after:
- 6 months
- 1 year [ANSWER]
- 2 years
- 5 years
Rationale: Nevada law generally requires a one-year waiting period before applying for reinstatement after revocation.
- On Nevada public works projects, certified payroll reports must be submitted:
- Quarterly
- Monthly
- Weekly [ANSWER]
- At project completion
Rationale: Contractors must submit weekly certified payroll reports to verify compliance with prevailing wage laws.
- Which type of insurance is mandatory for Nevada contractors with employees?
- Commercial property insurance
- General liability insurance
- Workers’ compensation insurance [ANSWER]
- Errors and omissions insurance
Rationale: Contractors with employees must carry workers’ compensation insurance under Nevada law.
16. A joint venture applying for a Nevada contractor’s license must:
- Only one member needs to be licensed
- Each party must be licensed in Nevada [ANSWER]
- Be incorporated in Nevada
- File no additional paperwork