QSP EXAM WITH 180+ QUESTIONS & CORRECT
ANSWERS LATEST 2024 EXAM GRADED A
A likely precipitation event is any weather pattern that is forecasted to have a ____% or greater probability of producing precipitation in the project area.
- 10
- 25
- 50
- 75
- 99 - ANSWER-C
A QSP is responsible for:
- Day to day implementation, inspections, and observations
- Amending the SWPPP as required
- Developing and certifying the SWPPP
- Certifying reports in SMARTS - ANSWER-a. Day to day implementation,
inspections, and observations
A storm that produces ½ inch or more of precipitation, with a 48 hour or greater period between rain events is a/an...
- Qualifying rain event
- Extended storm event 1 / 4
- Inactive storm event
- Unsafe monitoring event - ANSWER-a. Qualifying rain event
A temporary or permanent structural BMP that directs concentrated flows away from disturbed areas and prevents erosion is...
- erosion control
- run on/ run off control
- sediment control - ANSWER-b. run on/ run off control
Acceptable methods to demonstrate final stabilization include:
- 50%vegetative coverage
- 100% vegetative coverage
- RUSLE 2 method - ANSWER-c. RUSLE 2 method
Activities under the CGP include:
- Routine maintenance to maintain original line and grade, hydraulic capacity, or
- Disturbances to land surfaces solely related to agricultural operations.
- Clearing and grading 2 acres of land
- Discharges of storm water from areas on tribal lands. - ANSWER-c. Clearing
original purpose of the facility.
and grading 2 acres of land
All NAL data must be uploaded within ___ after NAL exceedance has been identified 2 / 4
- 24 hours
- 1 week
- 10 days
- 2 weeks - ANSWER-c. 10 days
Certain non-storm water discharges may be necessary for the completion of construction projects. Therefore the General Permit authorizes such discharges
provided they meet the following conditions except:
- Meet the NALs for pH and turbidity
- Not cause or contribute to a violation of water quality standards
- Comply with BMPs as described in the SWPPP
- Be infeasible to eliminate
- Causes or threatens to cause pollution, contamination, or nuisance - ANSWER-
- Causes or threatens to cause pollution, contamination, or nuisance
Hydrologic source controls are a design technique that minimize and/or slow the
rate of stormwater runoff from the site. Examples include:
- Reduction of pervious surfaces
- Use of landscaping as a storm drain treatment feature
- Drain rooftop downspouts to impervious areas
- Stormwater treatment facility - ANSWER-b. Use of landscaping as a storm
drain treatment feature
If the R Factor is ____, you can apply for the Erosivity Waiver. 3 / 4
- 1
- Less than 1
- 5
- Less than 5 - ANSWER-d. Less than 5
NEL Violation Reports must be submitted to State Board within 24 hours after
exceedance has been identified. NEL's are only subject to:
- Risk Level 1
- Risk Level 2
- Risk Level 3
- ATS Sites only - ANSWER-d. ATS Sites only
Once identified, dischargers shall begin implementing repairs or design changes to
BMPs:
- Immediately
- Within 24 hours
- Within 48 hours
- ASAP, but not more than 72 hours - ANSWER-d. ASAP, but not more than 72
hours
Permit Registration Documents (PRDs) shall consist of all of the following except:
- Site Map