WGU C176 Pre-Assessment Questions and Answers Graded A+

Which of the following is a project document created in the project closing process group that describes what went well and what didn't go well on the project? ✔✔Lessons learned

You're working for an organization and just learned that another organization with more power and influence is taking over your organization. What does this describe? ✔✔business acquisition

Which of the following describe the responsibilities of a project sponsor?

Each correct answer represents a complete solution. Choose all that apply.

  • Monitors the delivery of major milestones
  • Provides or obtains financial resources
  • Integrates all the components and artifacts of a project
  • Runs interference and removes roadblocks ✔✔A. Monitors the delivery of major milestones
  • Provides or obtains financial resources
  • D.Runs interference and removes roadblocks 1 / 3

What are the two types of charts that you might utilize to display the project schedule?

Each correct answer represents a complete solution. Choose all that apply.

  • Gantt chart
  • Run chart
  • Histogram

D. CPM

  • Milestone chart ✔✔A. Gantt chart
  • Milestone chart

In which type of organization does the project manager share responsibility for team member assignments and performance evaluations with the functional manager? ✔✔Matrix

Which of the following is a measurable value that shows whether the project is reaching its intended goals? ✔✔KPI

  • / 3

Your subject-matter expert tells you that her most likely estimate to complete her task is 40 hours. The task starts on Thursday, January 20, at 8 a.m. The team works eight-hours a day, and they do not work weekends. Which day will the task end? ✔✔January 26

You are the project manager for a small project that is in the Closing phase. You prepare closure documents and want to get them sign off. What will you do? ✔✔You will ask the sponsor to sign-off on the documents, showing that the project is officially closed.

A well-written change control process should include which of the following components?

Each correct answer represents a complete solution. Choose all that apply.

  • The cost of the change
  • Updated project planning documents
  • A description of the type of change requested
  • The amount of time the change will take to implement ✔✔A. The cost of the change
  • Updated project planning documents
  • A description of the type of change requested
  • The amount of time the change will take to implement
  • / 3

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Questions & answers
Added: Sep 5, 2025
Description:

WGU C176 Pre-Assessment Questions and Answers Graded A+ Which of the following is a project document created in the project closing process group that describes what went well and what didn't go we...

Get this document $30.00