WGU - C722 Questions and Answers Already Passed
Three essential drivers that must be achieved to generate positive characteristics in project teams ✔✔Cohesiveness, Trust, Motivation
The five stages Dr. Bruce Tuckman (1965) introduced of group development ✔✔Forming, Storming, Norming, Performing, Adjorning
Forming ✔✔In this stage, team members may be meeting for the first time. Often, no one really knows much about anyone else on the team. It may be premature to refer to this group of individuals as a team. It is a time of introduction and forming relationships and understanding from exchange of information.
Storming ✔✔Team members are beginning to know about each other, but they do not yet understand how to work together. Members may "jockey for position" within the team. The dynamics of working together beyond any written statement of "roles and responsibilities" are being established. Personalities surface, showing the strengths, weaknesses, and personal needs of each individual on the team. Integration into a team may come with some struggle and conflict.
- / 4
Norming ✔✔Team members have "figured out" how they will interact with each other. Working relationships are beginning to form. Trust and understanding is beginning to form between team members. They are beginning to feel comfortable working together and openly and willingly sharing information.
Performing ✔✔Team members are fully comfortable working together. Trust has been developed. Working relationships have jelled. Work is being conducted and project progress is occurring.
Adjourning ✔✔This only occurs when all the team's work has been completed and the team is no longer required. This may occur at any time in the project life cycle.
Co-located Teams ✔✔involves team members physically working at the same location or holding project meetings together in a common setup.
Virtual Teams ✔✔are teams whose members interact primarily through electronic communications. Members of a virtual team may be within the same building or across continents.
- / 4
Two common situations occur that may prompt a change to the baseline scope ✔✔The scope may be expanded to include additional functionality or the scope may be diminished due to changes in the project environment such as reduced funding or requirements or changing time/due date.
Scope creep ✔✔occurs when the project team integrates enhancements to the scope without proper evaluation and approval.
work performance data ✔✔will identify the work activities that are completed, partially completed, or not started.
risk register ✔✔is a list of potential risks, how the risks will be monitored, and what action will be taken should the risk event occur.
corrective action ✔✔is a document issued to identify quality failures and how they will be corrected. The deliverable itself may need to be reworked and the project plan may need to be revised to ensure that future deliverables do not include the same error.
The Four Categories of Change ✔✔Contingency plans, improvement changes, external events, scope change 3 / 4
The change management system ✔✔is in place to formally identify, evaluate, decide, and communicate project changes.
Recording ✔✔is the process of documenting and archiving project-related information.
Reporting ✔✔is a key nonverbal communications methodology used to inform and to document project information.
Weekly status reports that are often working documents for the team to communicate: ✔✔Accomplishments, Issues, Schedules, Resource utilization
Monthly status reports for senior stakeholders that would include: ✔✔Project overview bragging about progress, Issues including red light (critical) problems needing immediate resolution, yellow light items that are warning flags, and resolved issues, Current accomplishments, Future plans for the next month, Resource utilization and plans
Monthly Financial Report ✔✔showing progress against the budget quantifying monies spent and planned to be spent and identifying issues with recommendations for resolution