Page 1 of 120
1
WGU C783 PROJECT MANAGEMENT EXAM ACTUAL
EXAM ALL 300 QUESTIONS AND CORRECT ANSWERS
ALREADY GRADED A+
Q: Develop PM Plan Inputs - ANSWER-Proj. charter, outputs from other processes, Enterprise enviro. factors, and Org. process assets
Q: Develop PM Plan Tool & Techniques - ANSWER-Expert judgement, data gathering, interpersonal and team skills, and meetings
Q: Develop PM Plan Outputs - ANSWER-PM Plan
Q: Direct and Manage Project Work, Inputs - ANSWER-PM plan, proj. docs, approved change requests, enterprise enviro. factors, and org. process assets
Q: Direct and Manage Project Work, Tools & Techniques - ANSWER-Expert judgement, PMIS, and meetings
Q: Direct and Manage Project Work, Outputs - ANSWER-Deliverables, work performance data, issue log, change requests, PM plan updates, proj. docs. updates, and org. process assets updates 1 / 4
Page 2 of 120
2
Q: Manage Project Knowledge, Inputs - ANSWER-PM plan, proj. docs., deliverables, enterprise enviro. factors, and org. process assets
Q: Manage Project Knowledge, Tools & Techniques - ANSWER-Expert judgement, knowledge management, information management, interpersonal & team skills
Q: Manage Project Knowledge, Outputs - ANSWER-Lessons learned register, PM plan updates, and org. process assets updates Q: Develop Project Charter Inputs - ANSWER-Business documents, Agreements, Enterprise Enviro. factors, and Org. process assets
Q: Develop Project Charter Tools & Techniques x - ANSWER-Expert judgement, data gathering, interpersonal & team skills, and meetings. x
Q: Develop Project Charter Outputs - ANSWER-Project Charter, Assumption log
Q: Monitor and Control Project Work, Inputs - ANSWER-PM plan, proj. docs, work performance information, agreements, enter. enviro. factors, and org. process assets 2 / 4
Page 3 of 120
3
Q: Monitor and Control Project Work, Tools and Techniques - ANSWER-Expert judgement, data analysis, decision making, and meetings
Q: Monitor and Control Project Work, Outputs - ANSWER-Work performance reports, change requests, PM plan updates, and proj. docs updates
Q: Perform Integrated Change Control, Inputs - ANSWER-PM plan, proj. docs, work
performance reports, change requests, enter. enviro. factors, and org. process assets
Q: Perform Integrated Change Control, Tools & Techniques - ANSWER-Expert judgement, change control tools, data analysis, decision making, and meetings
Q: Perform Integrated Change Control, Outputs - ANSWER-Approved change requests, PM plan updates, and proj. documents updates.
Q: Close Project or Phase, Inputs - ANSWER-Project charter, PM plan, pro. docs, accepted deliverables, business docs, agreements, procurement docs, and org. process assets
Q: Close Project or Phase, Tools & Techniques - ANSWER-Expert Judgement 3 / 4
Page 4 of 120
4 Analytical Techniques Meetings
Q: Close Project or Phase, Outputs - ANSWER-Project document updates, Final
product/service/result transition, Final report, OPA updates
Q: Plan Scope Management, Inputs - ANSWER-Project Charter, Project Management Plan, EEFs, OPAs
Q: Plan Scope Management, Tools & Techniques (s) - ANSWER-Expert judgement, Data analysis, Meetings (s)
Q: Plan Scope Management, Outputs - ANSWER-Scope Management Plan
Requirements Management Plan
Q: Collect Requirements, Inputs - ANSWER-Project Charter, Project Management Plan, Project documents, Business documents, Agreements, EEFs, OPAs
- / 4