WGU C783 PROJECT MANAGEMENT EXAM LATEST

WGU EXAMS Aug 30, 2025
Loading...

Loading document viewer...

Page 0 of 0

Document Text

Page 1 of 131

1

WGU C783 PROJECT MANAGEMENT EXAM LATEST

2024-2025 ACTUAL EXAM VERSION A AND PRACTICE

TEST COMPLETE 350 QUESTIONS AND CORRECT

ANSWERS JUST RELEASED

WGU C783 PROJECT MANAGEMENT EXAM A

Q: What describes each of the deliverables and their components, the code of accounts identifier, estimates, resources, and criteria for acceptance? - ANSWER-The WBS dictionary.

Q: Which element of the scope statement documents the process and criteria you'll use to determine whether deliverables are complete and satisfactory? - ANSWER-Success criteria, otherwise known as acceptance criteria.

Q: Name the purpose of the scope management plan. - ANSWER-It documents the procedures for preparing the project scope statement, in other words, the WBS; defines how the deliverables will be verified; and describes the process for controlling scope change requests.

Q: Name the four types of project endings. - ANSWER-Starvation, integration, extinction and addition.

Q: This component of the scope statement documents the deliverables or items that will not be included in the project. - ANSWER-Exclusions Q: Name the steps in validating a project. - ANSWER-Validate the business case, and then identify and analyze stakeholders.

Q: Name the 9 knowledge areas outlined in the PMBOK Guide. - ANSWER-Scope, time, cost, quality, human resources, communications, risk, procurement and integration management 1 / 4

Page 2 of 131

2

Q: Name the steps in validating a business case. - ANSWER-feasibility study, justification, and alignment to the strategic plan

Q: In which project process group is the project charter document created? - ANSWER-Initiating

Q: Name the project process group that begins when the project charter is approved - ANSWER-Planning

Q: This system assures the project doesn't deviate from the planned requirements. - ANSWER- Change control system

Q: Name the term that describes processes that are repeated. - ANSWER-Iterative

Q: What type of requirement describes the elements required for a business process? - ANSWER-Business requirements

Q: What should come first, the project scope or the project charter? - ANSWER-The project charter.

Q: What is the purpose of the project charter? - ANSWER-The project charter normally approves the project and authorizes it to begin.

Q: What is the lowest level of the WBS? - ANSWER-The work package.

  • / 4

Page 3 of 131

3 Q: These help you determine whether the project is progressing as planned. - ANSWER-Key performance indicators (KPI's)

Q: Before assembling the project team, what needs must the project manager assess first? - ANSWER-Skills required by team members.

Q: Name the two significant processes you'll perform within the human-resources planning process. - ANSWER-Organizational planning and staff acquisition

Q: This process is where you'll choose team members or organizations who will work on the project. - ANSWER-Staff acquisition.

Q: What are the triple constraints according to CompTIA? - ANSWER-Time, cost and quality

Q: Name the major elements of a scope document. - ANSWER-product description, key deliverables, success and acceptance criteria, key performance indicators, exclusions, assumptions, and constraints.

Q: Performing this function on key deliverables results in the WBS. - ANSWER-Decomposition

Q: An activity that cannot start until its predecessor has concluded is said to have what type of logical relationship? - ANSWER-Finish-to-start

Q: Name the estimating technique that bases estimates on past projects of similar size and scope. - ANSWER-Analogous estimating.

Q: What is the first step in examining a scope deviation request? - ANSWER-Identify the cause. 3 / 4

Page 4 of 131

4

Q: What is the most often used logical relationship? - ANSWER-Finish-to-start

Q: Three point estimates use which three estimates to calculate the average estimate? - ANSWER-Most likely, pessimistic, and optimistic

Q: Placing activities into a logical sequence and determining their dependencies is called what?

  • ANSWER-Activity sequencing

Q: Describe float. - ANSWER-The difference in the length of time between the early start and late start or the early finish and late finish of an activity on the project.

Q: What type of scheduling chart represents task duration on a timeline and typically displays dependencies? - ANSWER-Gantt

Q: Name the two types of schedule formats used on most projects. - ANSWER-Gantt charts and milestone charts.

Q: Name the estimating technique that is a quantitatively based estimating method. - ANSWER- Parametric estimating.

Q: Gap analysis - ANSWER-Used to document services and functions that have been

accidentally left out, deliberately eliminated, or have yet to be developed.

Q: What chart tracks tasks, resource requirements, and quantity of resources? - ANSWER- Responsibility assignment matrix (RAM)

  • / 4

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: WGU EXAMS
Added: Aug 30, 2025
Description:

WGU C783 PROJECT MANAGEMENT EXAM LATEST 2024-2025 ACTUAL EXAM VERSION A AND PRACTICE TEST COMPLETE 350 QUESTIONS AND CORRECT ANSWERS JUST RELEASED WGU C783 PROJECT MANAGEMENT EXAM A Q: What describ...

Get this document $30.00