- | Page
IRONWORKER NCCER
QUESTIONS AND ANSWER S 100%
GUARANTEED PASS!
Question 1: ASSUMING A GRIP DISTANCE OF 1",
WHAT IS THE MINIMUN LENGTH OF THE BOLT
REQUIRED FOR A 3/4" DIAMETER BOLT?
CORRECT ANSWER : 2 1/4"
Question 2: THE LOCATION OF BRIDGING
DEPENDS ON THE LENGTH OF THE:
CORRECT ANSWER : SPAN
Question 3: BEFORE BUNDLES OF DECK CAN BE
LANDED ON A BAR JOIST, WHAT AC TION MUST
BE COMPLETED?
CORRECT ANSWER : JOIST MUST HAVE
BRIDGING INSTALLED
- | Page
Question 4: WHEN MATERIALS ARE BEING
HOISTED TO AN UPPER LEVEL, A TAG LINE IS
USED TO:
CORRECT ANSWER : HELP CONTROL THE LOAD
Question 5: ITEMS SUCH AS FIELD WELDING
INSTRUCTIONS, HANGERS, AND CONNECTION
DETAILS ARE GENERALLY FOUND ON:
CORRECT ANSWER : THE DETAIL DRAWINGS
Question 6: THE ABILITY OF A STRUCTURAL
STEEL COMPONENT TO RESIST PULLING FORCES
IS KNOWN AS:
CORRECT ANSWE R: TENSILE STRENGHT
- | Page
Question 7: WHAT TYPE OF DECKING HAS
IMPRESSIONS FORMED ON ITS RIB?
CORRECT ANSWER : COMPOSITE DECK
Question 8: THE GROUND FLOOR ELEVATION IS
SHOWN AS +100.25. THE ROOF TOP ELEVATION IS
SHOWN AS +130.50. WHAT IS THE DIFFERENCE IN
ELEVATION?
CORRECT ANSWER : 30'3
Question 9: IN WHAT DRAWING WOULD ONE FIND
THE CORRECT BOLT SIZE FOR A BEAM BEING
BOLTED?
CORRECT ANSWER : DETAIL DRAWING
Question 10: WHAT SHOULD ALWAYS BE USED TO
IGNITE A CUTTING TORCH?
- | Page